Hi,
To calculate multiple planning projects, it will be good to have all project in a selectable list to easily set priority on these different projects and make some try of calculation by changing priority, Hope my explanation are not too bad.
I don't understand the purpose as long as you can define a priority for each project
Hi Babynus,
My suggestion is not on adding priority to project but on how to manage quicker priority settings. Sometimes I need to do some tries to elaborate planning for multiple projects and for now it is not enough fast to change priority on multiple projects at a time.
If I see the point properly, it looks like a request for multiple changes function on projects - priority.
Klaus
yep !
So you just need to use the Multiple Update feature 😉
Works fine for priority 🙂
Just use dedicated button (the one with double floppy disks)
Thank you Babynus and Klaus, I didn't notice this button before. I've just try to use it but don't succeed in selecting multiple projects at a time except "all" or one ?
Just click on an item to select it (or de-select it if it is already selected)