Activity : fixed duration and no assignmen don't change state with progress

5 Posts
2 Utilisateurs
0 Reactions
866 Vu
jmmbb
(@jmmbb)
Posts: 561
Noble Member
Début du sujet
 
[#9341]

Hello,

i'm using fixed duration for activities with no assignment.
So, creating activity with fixed duration of 40 days and 20 of validated work.

As i reprot earlier, it is impossible to change progress in planning view (i see tickets records for that).
But, if i change progress via activity screen, state doesn't change (activity stay recorded with 30% progress - must be "en cours" - even with 100% progress (must be "done").

Related states exists in workflow for that activity type.
"recorded" is the first status, as usual (id #1, order 100)
"en cours" is the first "In progress" status (id #3,order 300)
"fait" is the first "done" status (id #4, order 400)

all state are accessible by user profile in workflow.

Can't reproduce on demo, i think option "manuel progress of fixed-duration activities" is not set to YES.

Regards,
 


 
Posté : 23/02/2024 7:40 pm
jmmbb
(@jmmbb)
Posts: 561
Noble Member
Début du sujet
 

Note that status don't change via Timesheet (see demo, activity #13).


 
Posté : 23/02/2024 7:50 pm
(@babynus)
Posts: 14952
Membre Admin
 

The automations on status change are based on Real Work entrey on Timesheet.
So in your case they are not triggered.


 
Posté : 28/02/2024 1:13 pm
jmmbb
(@jmmbb)
Posts: 561
Noble Member
Début du sujet
 

For testing, i use "as soon as possible" for activity planning


 
Posté : 28/02/2024 7:16 pm
(@babynus)
Posts: 14952
Membre Admin
 

Automation does not depend on planning mode : automation to change status only occurs on real work entry in timesheet screen


 
Posté : 03/03/2024 5:23 pm