activity in "Pause"
 
Notifications
Retirer tout

activity in "Pause"

4 Posts
2 Utilisateurs
0 Reactions
1,094 Vu
(@loicr)
Posts: 125
Estimable Member
Début du sujet
 
[#8668]

Good morning,

Somme activity on project are in "Pause", but they are planned and taken into account for planning, i don't understand why ?
normaly they are not planned and taken into account ?

The same for all project...

Thanks
LR


 
Posté : 19/12/2022 11:56 am
(@babynus)
Posts: 14952
Membre Admin
 

The status "pause" is not all.
You have to have the checkbox "pause" checked.
Defaut configuration forces this, but you may have changed it.


 
Posté : 20/12/2022 10:41 am
(@loicr)
Posts: 125
Estimable Member
Début du sujet
 

figer le planning X exclure du calcul du planning
mettre en pause X exclure du planning et purger le planifié actuel

2 points are checked so i don't understand ...
activities are always in global planning and in team planning in green.

LR


 
Posté : 20/12/2022 10:48 am
(@babynus)
Posts: 14952
Membre Admin
 

Ha, yes, they appear in the gantt, yes, they are not "removed".
But they are not planned any more (right click on the bar will show "no data")


 
Posté : 20/12/2022 11:15 am