Hi,
We are in 10.1.4.
automatically change status of parent does not work. when first child is moved to "in progress", parent does note move to "in progress".
Option is set in configuration panel.
Is there anything more to do / know to get this working ?
Workflow must allow the transition from current status to in progress.
Hi, Workflow still allow transition but this does not work
we are in 10.3.1
Any help ?
Hi,
Still the same problem in 12.3.2
Projet, activity (phase) and activity (task) workflows allow transition from assigned to in progress.
When task is changed to in progress, phase and project dont change and stay in status assigned
Any help will be great
First, global parameter must be enabled
Then, you need to understand that this feature does not change at each status change.
If changes only when "macro" status changes.
So when you move sub-activity to "In Progress", it checks the "handled" macro status.
But if "assigned" is already a "handled" status, status of parent does not move.
Hi,
First of all, I wish you and the entire Projeqtor team a very happy and prosperous 2026!
Secondly, thank you for your reply, but I'm not sure I understand. What exactly do you mean by "handled macro"?
Regards