Forum

Welcome to ProjeQtOr new Forum. We migrated old forum to the new website.
You will find all your posts here, with your usual account.
Just one point : you’ll have to reinitialize your password. Use “Lost password” feature.

Calendar problem
 
Notifications
Clear all

Calendar problem

5 Posts
2 Users
0 Reactions
5,071 Views
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 
[#280]

Hi,

Calendar behaviour is very strange: I can set only 1day off. When setting another one the first one setting coming back. Project plan/Gannt chart as well using weekend as working days

Regards,
Evgueni


 
Posted : 19 Dec 2011 14H27
babynus
(@babynus)
Posts: 14954
Main Contributor Admin
 

I can set only 1day off.

No, it's possible to set several off days.
Just click on the button "new"...
It seems this interface for calendar in not very user friendly as your are meny to ask questions about it.
An improvement is planned.

Project plan/Gannt chart as well using weekend as working days

No, planning is not using weekends as working days.
Gantt bars run through week-ends, as they go from start to end, but week-ends are not taken into account.


 
Posted : 19 Dec 2011 22H30
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 

So, for each day off we need to set a different calendar? For example settings for 26thg to 30th December should add 5 calendars?
Don't you think this is not quite right?

Regards,
Evgueni


 
Posted : 20 Dec 2011 10H59
babynus
(@babynus)
Posts: 14954
Main Contributor Admin
 

I agree this is not very clear.
Title of item should be "calendar exception".
There is one only Calendar, and in this interface you define exception days (off week days and open week-ends).

This interface will be improved to be more user friendly.


 
Posted : 20 Dec 2011 15H11
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 

Ok, thank you very much,

Regards,
Evgueni


 
Posted : 20 Dec 2011 15H23
Share: