Good morning everyone,

We are having problems completing a project.
See error message in pic "003".

However, the project no longer has any open times, see screen "001". There is a "0" or "0.00" everywhere.

If you then go to "In progress (in Bearbeitung)" > "Completed (fertiggestellt)", the error message "001" appears.

Link:
https://bmk.projeqtor.org/view/main.php?directAccess=true&objectClass=Activity&objectId=14506#

Do you have any idea what could be causing this? Any help would be appreciated.
With kind Regards, 
Benjamin Hahn


 
Posted : 15 Jul 2025 11H33
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Look at left work displayed on the item (not on the assignment)
If it's not null this can be because of :
 - exisiting sub-item with not null left
 - incorrect update
In this last case, try and change left for an existing value (>0) then back to zero : this should update the consolidated value.


 
Posted : 17 Jul 2025 12H52
(@bmk_it)
Posts: 2
New Member
Topic starter
 

Hello babynus,

Sorry for the late reply.

I spoke to my customer the other day and she simply said, “I already did that. It refers to a ticket that was not 0 but was then set to 0.”

So unfortunately, we're not getting anywhere.

Any other ideas?

Best regards,


 
Posted : 30 Jul 2025 19H31