Change the project of an activity => Problem with planning view

2 Posts
2 Utilisateurs
0 Reactions
2,787 Vu
(@jolla)
Posts: 1
New Member
Début du sujet
 
[#2805]

Hi,

when I change the project of an activity, the activity appears within activities list of the new project;
but not in the planning view, it remains in the planning view of the first project!!

Regards


 
Posté : 10 Déc AM 10:1212
(@babynus)
Posts: 14952
Membre Admin
 

Could you detail use case steps by steps ? On which screen do you operate ?
(show print screen)
Which version of ProjeQtOr ?
Can you check WBS for activity before and after ?

[Edit] I just tested and it's working as expected, so either you work on old version or it is a misunderstanding on "change project" or you used specific method that I did not think about.


 