[CLOSED] PlanningElement_validation : Can not add float value

7 Posts
2 Users
0 Reactions
9,339 Views
Vincent
(@vdeverre)
Posts: 38
Active Member
Topic starter
 
[#1136]

When I put a float value (like 0,5) the post request send the good value but when I reload activity the field value do not show my float value. It's a rounded value.


 
Posted : 29 Apr 2013 17H26
(@babynus)
Posts: 14952
Member Admin
 

Which screen ?
Which field ?


 
Posted : 29 Apr 2013 17H33
Vincent
(@vdeverre)
Posts: 38
Active Member
Topic starter
 

Sorry.

It is in Activity, in the section Activity Progress.

You can check all input delay/charge.

Thanks.


 
Posted : 29 Apr 2013 17H51
(@babynus)
Posts: 14952
Member Admin
 

Duration : only in full days, it is normal.
Project'Or RIA plans only in full days, so decimal duration has no meaning.

Work : decimal work works correctly.
Just be sure to use correct decimal point depending on your locale.


 
Posted : 29 Apr 2013 18H24
Vincent
(@vdeverre)
Posts: 38
Active Member
Topic starter
 

We can not work half-day ?
Some activities not need a full day to be done.

When I put a "5.0" I have an error but not with "5,0" so input check the correct decimal point.


 
Posted : 29 Apr 2013 18H48
(@babynus)
Posts: 14952
Member Admin
 

Yes, you can "Work" 0.5 day.
Work can be defined as decimal.
But this will be translated as a duration of 1 day.

Activity starting today and ending today lasts 1 day.
Project'Or RIA does not manage hours for start and end dates...


 
Posted : 29 Apr 2013 18H53
Vincent
(@vdeverre)
Posts: 38
Active Member
Topic starter
 

ok.

thanks


 
Posted : 29 Apr 2013 18H58