Hi,
I encountered an issue that some deleted tasks are still show in the Gantt view - Planning Menu. I checked in Activity Menu that the deleted tasks are not shown in Activities Menu and not the the activities table in the database.Would you share for any advice? 

 

Thanks,
Rainbow 


 
Posted : 02 Aug 2022 6H06
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Run the consistency check (and fix) in Administrative screen


 
Posted : 02 Aug 2022 10H55
(@rainbow)
Posts: 84
Active Member
Topic starter
 

Hi,

Thanks for your prompt advice. I ran the check and fix and have the error message as attached. My colleague have just requested to delete the project and created a new project.

Thanks,
Rainbow


 
Posted : 02 Aug 2022 11H08
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Which version of ProjeQtOr are you using ?


 
Posted : 02 Aug 2022 11H35
(@rainbow)
Posts: 84
Active Member
Topic starter
 

I am using version 8.6.6


 
Posted : 02 Aug 2022 11H40
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

We cannot support old versions in the forum.
Consider migrating to latest stable (V10.0.3) or subscribing to professional support


 
Posted : 02 Aug 2022 11H44
(@rainbow)
Posts: 84
Active Member
Topic starter
 

Noted. Thanks for your reply and advice.


 