Hi,

A lot of people use Projeqtor but i have a specific issue for one team composed of 3 ressources.
They completes their work every day, for each assigned task.

Sometines, on their timesheet, some values of a ressource on a task disapear, like there never been some allocation done by the ressource. I found a 0. Sure 100% that allocation have been done by ressources. Not always the same ressource, not always on a specific day or the same activity. It's weird.

Do you know if this is a bug or if there is an option somewhere to disable.


 
Posté : 08/04/2021 11:30 am
(@babynus)
Posts: 14952
Membre Admin
 

There is no option.
This may be an issue.

What is your version of ProjeQtOr ?
Can you please check on history, displaying "work" data to try and find action that could have set work to zero ?

 


 
Posté : 09/04/2021 6:16 pm