Dependencies between the activities

3 Posts
2 Users
0 Reactions
1,331 Views
(@navver1990)
Posts: 49
Active Member
Topic starter
 
[#7590]

Hello,
I am trying to create multiple activities in my project and dependencies(end-start) between them,but during testing for the same dependency,successor activity
getting started  before predecessor which is an issue.Can you help me with this.

Thanks,
Naveen


 
Posted : 20 Jun 2021 17H58
(@marylene)
Posts: 592
Contributor Admin
 

Hello

Dependency is one of the highest priority constraints, but if you have real work filled in on the successor or days planned in manual planning then it is possible that this dependency is not respected.

Real work and manual planning are the strongest constraints.


 
Posted : 21 Jun 2021 11H53
(@navver1990)
Posts: 49
Active Member
Topic starter
 

Okay,Thank you


 
Posted : 21 Jun 2021 13H48