Hi Babynus,
I've a project with many activities and ressources.
I've many imputations on these activities.
I've a resource with a cost (with no begin and end date) and I change this cost (in screen "Resources", part "Function and cost").
After the modification, cost in work table is correct for each activities.
But, the realCost in table planningElement are good or wrong, it depends on activities.
For some activities, realCost is calculated with the old resource cost; but on other activities, the realCost is calculated with the new resource cost.
I will try to find tomorrow where the bug is located , but if you have an idea...
Is the status of activities different ?
It is possible that changes is not dispathced to closed activities.
No, I thought about this problem, but the status is not different between these activities.
Today, I found another problem in calculating leftCost on activities:
I copied a database to have 2 projectorria with same data.
In one application, I joined a parent task to some activities .
=> leftCost on project is now different between the two databases!
And the difference correspond to dailyCost * n days.
It seems the some activities are now not take into account to calculate project leftCost...
idem for leftWork and realWork...
Consolidated values in planningElement table for project and high level activities are wrong
Very strange...