"exclude from planning and purge current planned" doesn't work anymore

3 Posts
3 Utilisateurs
0 Reactions
389 Vu
(@robra81)
Posts: 106
Estimable Member
Début du sujet
 
[#9987]

Hello,

following issue: since version 12.3.2 behaviour of "paused - exclude from planning and purge current planned" within activities changed. In former versions planned date was deleted when setting paused. Since version 12.3.2 planned date stays as calculated and will never be change. In my opinion former behaviour was better.

Thanks in advance
Ronny


 
Posté : 21/11/2025 9:48 am
(@maxime)
Posts: 268
Membre Admin
 

Hello,
It seems that this is a bug. Ticket recorded #10827
Have a nice day,
 


 
Posté : 02/12/2025 3:38 pm
(@babynus)
Posts: 14952
Membre Admin
 

Hi

This was suggestion from our Qlub of users : when item is "paused", last planned dates should be preserved.
It is just "paused", not purged.

But planned work is purged so that availability of resources is not used by pauses items.


 
Posté : 12/12/2025 5:45 pm