Gantt chart behaviour

11 Posts
2 Users
0 Reactions
11.7 K Views
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 
[#345]

I believe this is not how it suppose to be:

2 tasks - first is predecessor fo the second and both set to be as soon as possible:
XXXXXXXXXXXX - 1st
XXXXXXXXXXXXX - 2nd
if task 1 moved the second suppose to move as well, so we would expect:
XXXXXXXXXXXXX
XXXXXXXXXXXXXXXX
but instead we are getting:
XXXXXXXXXXXXX
XXXXXXXXXXXXX
Regards,
Evgueni


 
Posted : 09 Feb 2012 14H31
(@babynus)
Posts: 14952
Member Admin
 

Hi,
I'm almost sure planning reacts as expected.

But, to be sure, there are several constraints :
- you must re-calculate planning each time.
- this will correctly work for "as soon as possible tasks" only if some work is assigned (left work must exist)
- if task 2 has some real work, then it begins at find real work day, no matter the constraints (as it is some reallity, it overrides all planning constraints)

Can you check if you're on one of thoose cases ?


 
Posted : 09 Feb 2012 20H49
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 

Looking like it work if we are using days but it will create a mess if we are using hours in work assignment on recalculate


 
Posted : 10 Feb 2012 10H27
(@babynus)
Posts: 14952
Member Admin
 

Hi,
What is the lenght of overflow ?
Only one day or more ?

One day overflow can be normal : planning is correct and first task ends on one day, second starts the same day, just after.
Is this this case or do you face more complex issue ?


 
Posted : 10 Feb 2012 20H24
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 

It much more than one


 
Posted : 13 Feb 2012 10H53
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 

It is unpredictable. In some cases (projects) assigning work left hours will work OK but in some it still will create a mess...
It will be good to have an export available to send you some of this projects to look at

Regards,
Evgueni


 
Posted : 13 Feb 2012 15H01
(@babynus)
Posts: 14952
Member Admin
 

Yes please.
Send me an export so I can have a look.

thanks.


 
Posted : 13 Feb 2012 21H03
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 

Do you mean export into MSProject XML?


 
Posted : 14 Feb 2012 11H04
(@babynus)
Posts: 14952
Member Admin
 

I mean an export of the database, if your data is not confidential.
Or maybe just print screens.


 
Posted : 14 Feb 2012 12H36
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 

database is not possible - there are a lot of projects already, screen shots will not give you enough information i believe


 
Posted : 14 Feb 2012 12H53
(@babynus)
Posts: 14952
Member Admin
 

database is not possible - there are a lot of projects already

I understand

screen shots will not give you enough information i believe

Mybe at least screen shot of planning showing the 2 tasks, and 1 screen shot per task detail.
Thanks


 
Posted : 14 Feb 2012 13H44