Gantt chart - late as possible planning is not working. For task we have set end date and duration but task just not shown in Gantt chart even after recalculation
Posted : 22 Mar 2012 15H00
To be calculated, task must have some work (left work > 0)
Posted : 22 Mar 2012 15H33
Topic starter
Thanks - it works!
Posted : 22 Mar 2012 15H59