Hello,

I just installed Project'o ria, eveything seems to work except this :
I create tasks with links (predecessor and successor), but the Gantt diagram does'nt take care of the links after calculation. The tasks appear to be linked, but for example the successor task remains before the successor.
Is there something I missed ???

Regards,

Jean-Jacques


 
Posté : 3 Fév AM 01:022
(@babynus)
Posts: 14952
Membre Admin
 

What you get may happen if you define some planning mode based on work (for instance "as soon aspossible, wich is the default one) and you don't define any work : just try and define assignements to the tasks (activities) and set some assigned work, it should work better.
Or maybe you'd prefer define tasks as fixed duration...

Regards.


 
Posté : 3 Fév PM 16:022
(@jjclaudon)
Posts: 2
New Member
Début du sujet
 

Thanks, babynus, it works better now.
This tool is very complete, but a little bit difficult to use at the beginning (I was working with Open workbench before, which is nomore developped now).
Regards,
Jean-Jacques.


 
Posté : 6 Fév PM 13:022