Gantt display wrong in the duration bar

2 Posts
2 Users
0 Reactions
1,587 Views
(@j-buquet)
Posts: 1
New Member
Topic starter
 
[#7436]

Hi,

Something strange :
- If I charge 5 days on a task without assigning some days to a ressource, the bar is OK with 5 days
- With the same task, if I assign 5 days on one ressource, the bar is reduced at 1 day

Projeqtor 9.0.2


 
Posted : 22 Mar 2021 20H55
(@marylene)
Posts: 592
Contributor Admin
 

Hello,

First of all, I want to let you know that you are working on a version that has never been tagged stable. First, consider upgrading to version 9.0.6.
Maybe the problem will be solved after this.

If not, remember to check if your activity is not paused, it cannot be seen in your screenshot.
Otherwise, check the capacity of your resource, if its FTE is> = 5 then it will do what it was assigned to in 1 working day.

Do not hesitate to come back to us if the problem persists!
Good continuation


 
Posted : 24 Mar 2021 14H50