Hi,
I tried to import MS project in demo V9.0.2 and found out that the start and end dates are not filled in to the validated and requested dates.
Moreover, I would like to ask whether it is possible to supposed to import notes from MS project as well?
Thanks,
Rainbow
I tried to import MS project in demo V9.0.2 and found out that the start and end dates are not filled in to the validated and requested dates.
Yes, change of validated dates should be done through Projeqtro feature "Validate planning"
Moreover, I would like to ask whether it is possible to supposed to import notes from MS project as well?
I was note aware you coulde save note on MS-Project...
We'll have a look.