list of works for an activity shows with wrong details.

2 Posts
1 Utilisateurs
0 Reactions
556 Vu
(@chandrashekhar)
Posts: 275
Honorable Member
Début du sujet
 
[#9668]

Hi there,

I was checking with ProjeQtOR version 12.0.0 for timesheet: dispatch entry and then checked for report: list of works for an activity, it looks that hour units are showing not as entered in timesheet, in my case I had entered 1 hour each for two jobs, report is showing value 1/8 and also not showing total at the end. Please refer to the attachment.


 
Posté : 17/12/2024 11:54 am
(@chandrashekhar)
Posts: 275
Honorable Member
Début du sujet
 

Hi,

By adding another entry to re-check, I found that it's being added null value, that is why confusion arisen. Please refer to the attachment. I think there should not be added blank entry in table "workdetail".


 
Posté : 17/12/2024 12:19 pm