Hi,
When we want to plan in recurring mode, the weekly planning is not editable.
Clicking a cell does not do anything
any help ?
we are in last version
Which version are you using ?
We are in 10;3.1
User must have rights to enter real work for the corresponding resource.
Check if the user has the hability to enter real work for this resource on the timesheet screen.
Still so. but doesn't work
Hi, I finaly manage to acheive manuel planing for an activity.
My Profile was not one of the predefined profiles. So I had to swap to a predefined profile to acces this planning mode.
Now, I'm facing a strange issue. Even if I delete planned tasks on the calendar view, An occurence is still present in the agenda View at a date corresponding to the end planned ate of the activity.
Even if I calculate the planning, this task still present in the agenda View.
Any Idea ?
Hi,
I cannot reproduce : when I manually add planned date, I see it on the Diary, when I delete it, it is not present any more.
Could you please explain more precisely how you do it, show screenshots...
NB : possibly the resource can have entered real work, then deleting the planned date does not remove the real work.