Hi,
With ProjeQtOr V8.5.3 (266), previously created actions, with currently passed due date, did'nt trig "respect of planned due date" indicator (and consequently no pop-up alert).
In parallel, if I create a new item with a past due date, the indicator is triggered (as expected) and pop-up alert raises (also as expected).
Is that a regression from Ticket #4794 (see No more Projeqtor notifications ?
Thanks,
fmt
Hello,
Have you the indicator on the project ? or you just don't have the pop up?
And other users received the alert?
Hi,
As explained, I don't get indicator (neither pop-up alert).
Can you try to reproduce this on projeqtor demo please.
That we can have the same case as you, and understand the issue.
I couldn't exactly reproduce.
Nevertheless, the indicators finally triggered after I updated the untriggered actions... (i.e. I just modified a field value, saved, and missed indicator finally triggered - and pop-up raised).
Could it be related to Actions created under this previous Projeqtor version where there was a pop-up raising issue (see my message above) ?
Can you suggest a way to "update" items (like I did when I just modified a field value) to ensure they will be reconsidered in the indicator triggering process ?
Thanks,
fmt
Hello,
the problem is possibly with the cron, if it is not running.
Check it, and if it's running restart it.
Reproduced on action #20 https://demo.projeqtor.org/view/main.php?directAccess=true&objectClass=Action&objectId=20
Due date was 06/08/2020 and I didn't see any "respect of planned due date" indicator until I updated description field
On demo, CRON was stopped.
I resatarted it.
Please try again.