Forum

Off days on plannin...
 
Notifications
Retirer tout

Off days on planning

2 Posts
2 Utilisateurs
0 Reactions
2,235 Vu
(@bion)
Posts: 70
Active Member
Début du sujet
 
[#5158]

Hello,
Is this normal that i get, on the planning calculation, two weeks of off days in my project from 8th May to 19th May (if grey columns means it's an off day).
I've got the given calendar below for the only resource who's working on the project


 
Posté : 16 Mai PM 13:055
(@babynus)
Posts: 14952
Membre Admin
 

The planning is not restricted to a resource, so display is based on default calendar (the one with id 1)
NB : after change on this calendar, you need to disconnect / reconnect to have correct display on planiing


 
Posté : 16 Mai PM 13:055
Share:
Retour en haut