Hi,
Got new problem in planning with v.3.1.4 - not started tasks on recalculate moved into 2014 (see enclosed image)


 
Posted : 11 Feb 2013 18H54
(@babynus)
Posts: 14952
Member Admin
 

Hi,

V3.1.4 fixes one bug in previous version : when not defining project for planning, all accessible projects are planned.
Before fixing, projects should be planned one by one only.
So tasks on some projets would not move, because availability would not be shared between projects..
This may explain why this tacks moved.

But could you give more information ?
Is the planned date correct depending on priorities, dependencies, availability of resources ... on all projects ?


 
Posted : 12 Feb 2013 1H23
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 

To do this kind of analysis on all 67 projects will take a while...I believe that people involved in this project not involved into any other projects, so this should not affect this tasks. Moreover the previous group of tasks (Iteration1 ) which already started have not moved. And if the date in planned will be not 2014 but 2013 it all will be Ok


 
Posted : 12 Feb 2013 10H23
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 

I have discovered some information - look at the enclosed screenshot for resource planning and you can see that for some reason some tasks are extremely long on this graph...


 
Posted : 12 Feb 2013 10H33
(@babynus)
Posts: 14952
Member Admin
 

Hi,
Could you provide print for dates of the 3 "long" tasks.
The split of this tsks is strange.
For resource planning, you can have 2 parts in bars : grey part reflects the "real work" period. The green (or red if late) part reflect the "planed" period.
This split aims to point out tasks that are split, from real work already done to planned start.
What is stange for these tasks, is that real work bar ends must later than planned work...
It seems there is some real work in 2014...
Could you check this ?


 
Posted : 12 Feb 2013 14H43
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 

Thank you very much - found task where real work been booked to 2014!!!
Now everything is OK!


 
Posted : 12 Feb 2013 15H13
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 

May be we should have an option to set the limit how far in advance people can do real work allocation?


 
Posted : 12 Feb 2013 15H40
(@babynus)
Posts: 14952
Member Admin
 

It is an interesting improvement.
Ticket #1001 registered.
One idea could be to forbid (or raise alert) when real work is entered after max(validated end date, planned end date) for a project.


 
Posted : 12 Feb 2013 16H09
Klaus
(@climb4fun)
Posts: 449
Contributor
 

Yes, very good idea.

Klaus


 
Posted : 13 Feb 2013 19H42