After upgrade form 9.0.5 to 9.1.0 preset project "Leave Period" is invisible, and no view or project selector displays it; it exists in database; the same issue persists after upgrade to 9.1.1
Hi,
Normal, this project should never have been displayed, it is an internal (tecnical) project.
Yes, and it was a mistake.
glad to hear that, for appearance of this project was really annoying
Hello,
I'm on V9.3.1 and "PROJEKT - LEAVE PERIOD" is visible in some views like "Today" or "report work tim" (don't know correct english term, in german it's "Ist-Arbeit reporten") - is it a bug or is it possible to hide the "PROJEKT - LEAVE PERIOD" erverywhere?
Thanks
Ronny
Display in Today view may be an issue. I'll have a look.
Display on reports is normal as it contains value for work, so it need to be displayed to have correct complete values.
Thank you for your respond and I have to say that ProjeQtOr is the best open source tool I've ever seen!
One little addition: I don't mean the reports but the page where the user/ressource can report his work per activity and I think it's confusing to see leave projects here that he isn't able to report work to - maybe as an info, that he was absent this day (is it possible for me, to change the name of the leave project to something german or may it lead to problems?)
Thank your very much for your answers and the great work on this tool!
Ronny
Hi,
Behavior of Timesheet is normal.
On Timesheet you can see data entered on Leave Project through the Leaves System (HR module).
This system bring some validation process : the resource created the leave period, submits it, then hos manager can validate it.
So this cannot be changed on the Timesheet. It is displayed only.
Note that on Timesheet Submitted leave period appears as planned work and Validated leave period appears as real work.