I've a problem when I change information in calendars.
Calculations are correct, but there is no change on the representation of working days or not.
It is necessary to disconnect and reconnect to see the changes.
Can you confirm this behavior? A correction is possible?
We are in the analysis phase before deployment and this is a problem for us.
Thanks.
Hi,
Do you mean that you change working/off days in a calendar and you don't see changes ?
Where do you expect to see these changes ?
=> in planning : only default calendar off days are displlayed
=> agenda : should be correct
=> real work allocation : should be correct
Hy,
absolutly !!!
I change just in default calendar .
So, in planner :
After change, in planning, the new off days isn't display in grey.
After disconnect/reconnect : it's OK.
In Agenda : it's correct immediatly
The real work allocation : it's correct immediatly.
Is it possible that the frame calendar isn't redraw and that just the gantt bar are recalculated ?
Is it possible that the frame calendar isn't redraw and that just the gantt bar are recalculated ?
No exactly.
It is because Gantt is drawn is Javascript, and using off days table stored in Javascrtipt.
And this list is loaded only on start page...
Ticket #1402 recorded to look for an improvement.
Does not seem to be blocking 😉