[SOLVED] Activity does not repect the assignment

2 Posts
2 Utilisateurs
0 Reactions
3,671 Vu
 Loic
(@lfd)
Posts: 6
Active Member
Début du sujet
 
[#3048]

I have a problem with one lign of activity.
This one is affected at one resource.
But when an other resource go to imputation sheet, activity is present.

When i go back to the activity sheet, the resource is allocated to this activity.


 
Posté : 15/02/2016 12:38 pm
(@richard-pare)
Posts: 165
Estimable Member
 

It's normal behavior of project type: "Administrative".
For this kind of a project everybody can put real work on tasks.
An assignation is automatically created.


 
Posté : 15/02/2016 4:19 pm
Share: