[SOLVED] left work in activity not updates auto.

6 Posts
2 Users
0 Reactions
1,476 Views
(@chandrashekhar)
Posts: 275
Contributor
Topic starter
 
[#8239]

Hi 
In Activity under Progress tab ->Assignment:  If real work hours are already available & Assigned hours are being added later then left work is not being updated auto!
 


 
Posted : 28 Apr 2022 12H59
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Cannot reproduce.

Please describe use case in detail, step by step.


 
Posted : 28 Apr 2022 14H04
(@chandrashekhar)
Posts: 275
Contributor
Topic starter
 

Please find the attachment for use case in detail, step by step.


 
Posted : 28 Apr 2022 15H44
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Hi,

Behavior is normal : You had 0 assigned, 0 left, and you entered 12 for real. OK
After that, you enter 24 assigned, so it means you add 24 to existing, so left is 24. You'll have to change it manually if it's not whan you expect.
 


 
Posted : 28 Apr 2022 16H15
(@chandrashekhar)
Posts: 275
Contributor
Topic starter
 

Sorry Friend,

But If you add assigned first & then input real, it will work fine for pending as per expected! I can't understand how you are accepting it as Okay?!


 
Posted : 28 Apr 2022 16H23
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Because left in not alwayd Assigned - Real.
Imagine you have Assigned = 10, entre Real = 7, left is automatically calculated to 3, but resource can change Left to 5, so reassessed is now 12 (assigned is underestimated)
😉 This happens all the time.

Then if you add extra work and set Assigned=15, then left will be set to 10 (you add 5 to assigned, so Left is increased of 5). We don't mind about existing real.
This works the same way is assigned is zero... if you Add some assigned work, left will be added the same added value, whatever existing real work.
Once again, if it's not what you expect (for instance you want to fix some incorrectly assigned work) you can very easily change the left work.


 
Posted : 28 Apr 2022 16H32