Hi Expert,
Hi Expert,
I used feature Multiple update in resources to replace max daily work with 9 in all my resources, it replaced with 72!
when I replaced max daily work with 1 it replaced with 8. What is the logic behind this?
Please help me to know the reason.
Version 9.5.5
Posté : 02/07/2022 4:59 pm
Multiple update requires inout in days