Hi,

I changed the global parameters/activity/planning - "show resource in Gantt" setting to 'name', but the display of resoruces in Gantt table column and chart area still remain as resources initials instead of resources names. I also tried to clear cache but still no changes. Would you advise how to enable or any other settings required? I included screenshots as attached.

Thanks,
Rainbow


 
Posted : 10 Mar 2021 6H13
 M
(@mkavurcic)
Posts: 43
Active Member
 

Try - User parameters -> Display ->Graphic Interface behaviour -> show resource in Gantt


 