Dear all,

On specific project, to change priority, we put project at 700 instead of 500 but all tasks are planned before project with activities at 500.

I don't understand what happen. It seems that priorities are not taken into account. ( we also move project to have lower wbs : no change ... )

We put also subtask and sub activities at 700 but result is the same, after new calculation, the task is done as soon as possible despite other projects.

i've put project in pause to avoid the tasks to be planned before others.

Sincerely

LR

ps: Projector V11.0.0 with mysql on ubuntu 22 php 8.1


 
Posté : 05/10/2023 5:32 pm
(@babynus)
Posts: 14952
Membre Admin
 

Planning priorities depend on several factors, includng planning mode.
Have a look at user manual for more information.


 
Posté : 09/10/2023 9:05 pm
(@loicr)
Posts: 125
Estimable Member
Début du sujet
 

Thanks a lot, i've got planning end date priority check in global parameter !

Thanks
LR


 