The "Divide this assignment" does not work as expected

2 Posts
2 Utilisateurs
0 Reactions
2,482 Vu
(@narayanaras)
Posts: 150
Active Member
Début du sujet
 
[#5134]

In an experiment, I started with this task:

Then I decided to split the work assigned to Akshath Hegde, by adding a new resource.
I pressed the

button next to Akshath.

A window popped up, in which I specified a new developer.

I noticed that ProjeQtor had automatically assigned 15 hours of work to Sangeetha.
This was logical, because Akshatha was assigned 30 hours earlier.
I assumed that now Akshath is left with 15 hour of work.

But the final result shows that now Akshath is left with no work at all! [BUG#1]
The total hours for the task are reduced from 45 hours to 30 hours now. [BUG#2]


 
Posté : 4 Mai AM 10:055
(@babynus)
Posts: 14952
Membre Admin
 

Hi,

It seems result is not as expected when unit for work is "houré (works fine with "day")
Issue recorded as Ticket #3363


 
Posté : 4 Mai PM 12:055