Validated time is not being totalized in the parent activity

2 Posts
2 Users
0 Reactions
1,508 Views
(@luchomqz)
Posts: 17
Active Member
Topic starter
 
[#8378]

Hi

In the planning view, the sum of the validated times of the child activities is not being totalized in the parent one.
We are running projeqtor on PHP 8.1

Thanks


 
Posted : 25 Jul 2022 21H29
(@marylene)
Posts: 592
Contributor Admin
 

Hello

Have you checked the global parameter > Planning > Automation > consolidate validated work & cost
If it is NEVER then the validated work will not be consolidated


 
Posted : 27 Jul 2022 12H59