Hi
In the planning view, the sum of the validated times of the child activities is not being totalized in the parent one.
We are running projeqtor on PHP 8.1

Thanks
Posté : 25/07/2022 9:29 pm
Hello
Have you checked the global parameter > Planning > Automation > consolidate validated work & cost
If it is NEVER then the validated work will not be consolidated