Be careful the rate is 0 on your pic below ; give a value and then ? ok the limited period is good in our case
I asked you if your resource is allocated on projet with a limited period ?
HI, Have you also checked if a period has been allocated of this resource on this project ? Have you thought to replan the planning ?
HI, Are you really sure that no one had filled workload on this activity into the past regardless tickets ?
acces mode
HI, You have to create a special profil allowing this and modify the rights on profils for people working on tickets. So you have to go straight ...
ticket will be create into our roadmap, seems fine.
Hi Yes you can. Color is not given automaticaly when created, only manually. Using the buttom multiple update you can change at once the colors of ...
HI, From wich version to wich version do you migrate ? Have you checked profil's right on timesheet screen? Have you check that project are not l...
hi, I did not read details of your organization, but i point out instantaneously that : it seems that the sort order of the profiles and the corres...
Hello, You can use base line to compare your project to them. You can also take pictures of reports or gantt view to attach them in " attached files"...
HI, We have get the explanation. When you choose a start date a saturday or a sunday, the application counts one day of duration more, following sat...
We have found something weird yes ! we are checking it ! you could be right ...
Screen : Absence is linked to resource Field : Validated dates are linked to the project. It is what you expect. There is no direct link beetween th...
Are you kidding me ?