[SOLVED] duration in activity counting.

valided dates and absences are not directly linked. It seems you do not have yet enterly undestood at least one of those concepts Please read the use...

Il y a 4 ans
Répondre
[SOLVED] duration in activity counting.

At the first glance, reading one of your pictures, I notice you did not replan your project before comparing them. ..... and what is matter, please e...

Il y a 4 ans
Répondre
[SOLVED] duration in activity counting.

HI, I do not understand what you are doing. Training sometimes is welcomed, please refer to our professional services

Il y a 4 ans
Répondre
Change Workflow

Give a workflow fisrtly on type of project Then your project with its type will follow the workflow ascribed to this type

Il y a 4 ans
Répondre
History of Assignment

HI, You want to read the history on this screen, under those informations ? In that case, nowadays, .it is not possible

Il y a 4 ans
Répondre
History of Assignment

When history is displayed, click on " show work", you ll get all informations you are looking for.

Il y a 4 ans
Répondre
Il y a 4 ans
Répondre
Il y a 4 ans
Répondre
Impossible to leave "manual" planning mode as some "real" planning exists

What is your matter ? Yes on fixed duration the progress could be calculated "manually" based on valided cost or are you talking about the fact that ...

Il y a 4 ans
Répondre
Impossible to leave "manual" planning mode as some "real" planning exists

Sorry, but i still do not undersand your request about tthe link beetween, progress, planning mode and fixed duration. Could you explain again. Thank...

Il y a 4 ans
Répondre
[SOLVED] filter not shows result as expected!

hi use that one : <= and 99 % it works well

Il y a 4 ans
Répondre
Impossible to leave "manual" planning mode as some "real" planning exists

HI, Which message ? ( not attached) What the meaning of the last sentence ? Do not understand.

Il y a 4 ans
Répondre
Automatic planning in ProjeQtOr

Hi, Thank You. An efficient project management can never be entirely automatically driven by software. The choice to use one planning option rathe...

Il y a 4 ans
Répondre
Automatic planning in ProjeQtOr

Play with priorities on projets, or on activities, or change your wbs, or create a dependency, or workload differently each resource, why not with a s...

Il y a 4 ans
Répondre
Automatic planning in ProjeQtOr

hi, There is no restriction at all ! Projeqtor plans AA because it is the first activity on your planning work breakdown structure. Moreover you use...

Il y a 4 ans