Hi,
In activity, I would lik to leave the manual planning mode, but I got this message.
However, I don't see any real planning for this activity (planned dates are grey and empty).
Also, why manual progress is limitated to fixed duration ?

Thanks in advance


 
Posted : 24 Jun 2022 16H07
(@alain-fourastie)
Posts: 366
Active Member Moderator
 

HI,

Which message ? ( not attached)
What the meaning of the last sentence ? Do not understand.


 
Posted : 24 Jun 2022 16H11
(@laurentc)
Posts: 100
Active Member
Topic starter
 

The message is impossible to leave "manual" planning mode as some real planning exists.
Concerning the last sentence, it seems that the setting manually the progress of an activity is limitated to fixed duration planning mode. But why this limitation ?
Thanks in advance. 


 
Posted : 24 Jun 2022 16H17
(@alain-fourastie)
Posts: 366
Active Member Moderator
 

Sorry, but i still do not undersand your request about tthe link beetween, progress,  planning mode and fixed duration. Could you explain again. Thank U;


 
Posted : 24 Jun 2022 16H26
(@laurentc)
Posts: 100
Active Member
Topic starter
 

Fixed duration is one of the available planning mode for activities.
Setting the planning mode to fixed duration is mandatory to set manually the progress of the activity. But why such a limitation ? Why this feature is not available in manual planning mode for instance ?

 


 
Posted : 24 Jun 2022 16H32
(@alain-fourastie)
Posts: 366
Active Member Moderator
 

What is your matter ? Yes on fixed duration the progress could be calculated "manually" based on valided cost  or are you talking about the fact that progress  is calculated depending on the duration if no workload had been given ? On first case, you can integrate the progress of this single activity which  you do not master ( supplyer, another office, another team, ...) on your whole progress of the project to get a better real value than none.
On manual planning progress is only  calculated depending on the workdone compare to the whole one ( done + left) cause you have given and planified real workload by your own because you master ( you manage)  this activity.


 
Posted : 24 Jun 2022 17H38
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Hi,

I thing you make a confusion beetween "Manual Planning mode", and "Fixed duration mode" that give acces to manual input of progress.
"Manual planning mode" give possibility to enter planned dates through "Planned intervention screen". You cannot change the mode if some planned intervention exist.
For "fix duration mode", if you select the option in global parameter, you can manually enter progress on the activity (as long as there is no assignment on the activity)


 
Posted : 27 Jun 2022 14H13
(@laurentc)
Posts: 100
Active Member
Topic starter
 

Clearer! Thanks a lot.


 
Posted : 28 Jun 2022 18H01