Hello, I was testing both latest releases and wonder if you found the root cause to the issue I described previously ? With large projects, the gant...
Hello, Thank for your feedback. Please see attachment with some screenshots. I cannot see any errors in the logs. Neither Apache- neither ProjeQtOr....
I modified : 1. line 1632 into $resultArray[$i]['pduration']=workDayDiffDates($resultArray[$i]['pstart'],$resultArray[$i]['pend'], $resultArray[$i][...
Line 1632 calculates duration. Some sections, I can export, some I cannot. I do not see any issues on the display.
Is there anything from my side I can do to help you debugging the error?
Which calendar is being used for the planning calculation ? Task "responsible" or "task assigned resource"? Apparently, I cannot get it work.
Thank you. I tested your procedure. It works if you grant "Updater", but then it also has access to change other things on the activity. I am just loo...
Thank you for the suggestions. I have tried as well. When using sub-projects, you cannot set links between. I use filters, but apparently, not all li...
Yes, both browsers are up-to-date. I use 10.4.2 (but seen issue with previous versions as well). Server side meets all the requirements. I can load up...