Thanks Babynus.
Yes, it is but on the Ticket 1264, we could load a default filter for each profile. It could be a good idea to have the possibility to export and i...
Thanks, I have a better understanding about how to use the priority on ProjeQtOr.
I tried with version 5.2.2 and it works fine. Thanks
Excelent, thanks.
Sorry, I repeat my question with more details. Thanks, I will do it, but just to be sure, the problem is solved on v5.2.2? or I need to upgrade Pro...
Thanks, I will do it, but just to be sure, the problem is solved on v5.2.2? or I need to upgrade ProjeQtOr AND Php? Because the upgrade of Php is ...
I think the problem is on the name; space on the name is not resolved correctly
Update the assign work (travail assigné) for the user CP1), with the pen on "participants" tab and rebuild the planning if it is necessary.
Is it necesary to replan to take in charge the update of the priority even if "automatic run plan" is enabled? Could you confirm me ?
Thanks Babynus, it takes sense...that's why I need to change the priority of the sub project (if exists). :woohoo: Thanks a lot for sharing your ...
Thanks Babynus, the issue was solved with this workaround.