Hello If I understand your explanation : - I define an indicator on activity ("reassessed work compared to validated work"), with the threshold of 1...
I tested 5.2.3 this morning. The issue is fixed, it works great, thanks 🙂
Great 🙂 Thanks
Reproduced on demo : Project : RegularFullDays Resource : albert Assigned 3 days "regular in full days" in february 2016 -> The issu...
Yes I have recalculated the planning. Seems weird to me, if I do a test on a newly created activity, it works well. But the issue appears on some p...
Yes, but even with "regular in full days", 0.1 days are planned : Is there any reason why the planning calculation would to that ?
That is exactly what I did :
Thanks for this helpful doc That is what I understood, I should have : But instead the last day is splitted in 0.1 or 0.2 workloads like ...
OK, I will experiment this It is less work than defining periodic meetings anyway Thanks !
Hello I have the same issue, except that Joe is off every Wednesday afternoon. -> I tried with FTE = 0.9 (like recommended in manual), but it gen...
OK I will investigate custom reports and let you know Thanks for the margin, it is actually much more logical like this