Hello, I finally found where was the left work. It was in meetings that were not closed. Not a bug, I close the issue.
Hi again, I have an other task with similar problem. Once again, only 1 ressource assigned to the task, no more left work on the ressource. But thi...
Hi Pascal, Thanks for the quick reply. Effectively we were in case 2 => planning not recalculated for one of our projects.
Hello Pascal, Thanks for the quick reply. I Not a bug at all finally.
Hi, 1) How can we put/get correct data for future bills and payments ? I think that just enter bill, on some "prepared" status, with expected amou...
Hi, Thanks for the reply, I modified the file model/CommandMain.php with $work += $line->numberDays; and now it's working correctly (after havin...
Ok that's clear, thank you !
Hi Pascal, This works thank you !
Hi Pascal, Thanks for the answer. The workaround is working well. One more question, how can we put dates in start and end dates ? So I could u...
Hi Pascal, Sorry for late reply. I updated to version 7.1.5, tried on a fresh Chrome (so no cache), and I get the same type of error : I'...
Hi, I'm still on v7.1.4, I can update to v7.1.5 and retry. I also had a look at the .js file and did not see anything Strange but I'm really not an ...
Hi Pascal, Looking at the error log from Apache, it was linked to a timeout : PHP Fatal error: Maximum execution time of 30 seconds exceeded in /...
Hi Pascal, Here it is. Both requets have the same. Answer is empty in both cases.
Hi Pascal, Here are the captures of the Network tab :
Hi, Sorry for late answer, I was off for holidays. I tried again this morning, after having cleared the cache (Microsoft Edge), and the result is ...
Hi Pascal, Please find it attached. Nothing related to the error I got (which occured around 15h00 for the 1st trial). projeqtor_20180801.log.