replacement of allocated resources

Hello @#Chris, i don't have the response, but some questions. This resource has been assigned in some tasks on your project ? Has he consumer t...

Il y a 9 ans
Répondre
Project Expense

Hi, thanks for your feedback. this could be useful for projeqtor's users. I don't use this part but soon certainly. Have a nice day.

Il y a 9 ans
Répondre
Project Expense

Hi, good news ! Create a new expense triggered refresh of amount of project. However, if you modify again a value of expense, only one line of ...

Il y a 9 ans
Répondre
Project Expense

Hi, i am a beginner of projeqtor. but i wonder if reports in "follow-up -> reports -> costs" that you can see, seems to be ok and then ref...

Il y a 9 ans
Répondre
How to run scheduling calculation ?

Thanks for all @babynus. Sure,and i wouldn't know to remember each step that i have made at the beginning, to get problems observed. Thanks ag...

Il y a 9 ans
Répondre
How to run scheduling calculation ?

Thanks ! I'm in progress due to your help ! Well graded for the function of resource on the assignment. I edited my previous post, because i hav...

Il y a 9 ans
Répondre
How to run scheduling calculation ?

Hello, Maxime has been assigned on 1.5,1.6,1.7 tasks. Scheduling calculation didn't take into the fact of Maxime is days off and come back to 29 A...

Il y a 9 ans
Répondre
How to run scheduling calculation ?

perfect. Do you know the reason whose explains that the scheduling calculation planned for Maxime the 23,24,25 August ?

Il y a 9 ans
Répondre
How to run scheduling calculation ?

i didn't fill the field "rate (%)" for the resource "Guillaume".Rate = 0% means resource cannot work (or at least won't be planned) on the task. ok...

Il y a 9 ans
Répondre
How to run scheduling calculation ?

Hello, yes but i launch each time, the scheduling calculation. 2.1 task i didn't fill the field "rate (%)" for the resource "Guillaume". I se...

Il y a 9 ans
Répondre
How to run scheduling calculation ?

i had clicked on the button "calculate activities planning" and i havec this message. But i don't get this message on all bars. For example, not for...

Il y a 9 ans
Répondre
How to run scheduling calculation ?

Thanks for yours responses. 1) this 1.5 task seems to be "as soon as possible" (shown on the picture) the "congés & RTT" project defined on "A...

Il y a 9 ans