Hello @#Chris, i don't have the response, but some questions. This resource has been assigned in some tasks on your project ? Has he consumer t...
Hi, thanks for your feedback. this could be useful for projeqtor's users. I don't use this part but soon certainly. Have a nice day.
Hi, good news ! Create a new expense triggered refresh of amount of project. However, if you modify again a value of expense, only one line of ...
Hi, i am a beginner of projeqtor. but i wonder if reports in "follow-up -> reports -> costs" that you can see, seems to be ok and then ref...
Thanks for all @babynus. Sure,and i wouldn't know to remember each step that i have made at the beginning, to get problems observed. Thanks ag...
Thanks ! I'm in progress due to your help ! Well graded for the function of resource on the assignment. I edited my previous post, because i hav...
Hello, Maxime has been assigned on 1.5,1.6,1.7 tasks. Scheduling calculation didn't take into the fact of Maxime is days off and come back to 29 A...
perfect. Do you know the reason whose explains that the scheduling calculation planned for Maxime the 23,24,25 August ?
i didn't fill the field "rate (%)" for the resource "Guillaume".Rate = 0% means resource cannot work (or at least won't be planned) on the task. ok...
Hello, yes but i launch each time, the scheduling calculation. 2.1 task i didn't fill the field "rate (%)" for the resource "Guillaume". I se...
i had clicked on the button "calculate activities planning" and i havec this message. But i don't get this message on all bars. For example, not for...
Thanks for yours responses. 1) this 1.5 task seems to be "as soon as possible" (shown on the picture) the "congés & RTT" project defined on "A...