Why do all activities appear with a duration of 1 day in the planning view ?

Right ! it was uncorrectly set. I thought 'Capacity' was the number of worked days per year. Thanks you very much ! Sandrine.

9 years ago
Reply
Why do all activities appear with a duration of 1 day in the planning view ?

The planning scale is correctly set. You will find a screen copy attached. Thanks for your help. Sandrine.

9 years ago
Reply
Why do all activities appear with a duration of 1 day in the planning view ?

Thanks for your answer. I tried it already but the planning didn't change. Do you have another idea ?

9 years ago