Hi everyone,
I'm a new user and I'm facing diffultives in activities setup.
I've just created an activity with an estimated workload of 6 days.
This activity has been assigned to one member (100% capacity on the project).
I expected to see on the planning view a 6 days bar.
But the activity appears with a duration of one day.
Furthermore, in the activity view, in the 'planned days' column, only one day is indicated.
I don't understand why.
Could you explain me ?
Thanks,
Sandrine.
Thanks for your answer.
I tried it already but the planning didn't change.
Do you have another idea ?
Can you verify the "capacity" of the resource " Thirion Lannister " ? ( he died on the episode 3 *joke*)
He can do few days ( depend of capacity ) in one day . You can have more detail of this in Report->Planning->Monthly Planning resource/project/activity .
Right ! it was uncorrectly set.
I thought 'Capacity' was the number of worked days per year.
Thanks you very much !
Sandrine.