[SOLVED] Wrong list of parent activities

I wanted to, but failed 🙂 I think it's really linked to a user being affected to just one project - so I don't think I can reproduce it with one of ...

10 years ago
Topic
Replies: 1
Views: 2915
Reply
[SOLVED] Wrong list of parent activities

Extra notes: - this is only reproduced when project selector = 'All projects' - this is only reproduced at first loading of the new activity: if...

10 years ago
Topic
Replies: 8
Views: 7487
Topic
Replies: 1
Views: 2419
Reply
[SOLVED] Team Notes & Attachments

OK, I understand indeed the difference for admin as technical profile, not necessarily "all-seeing" 🙂 Problematic use case will anyway be fixed by T...

10 years ago
Topic
Replies: 2
Views: 2491
Topic
Replies: 1
Views: 2692
Reply
Import activities with tree structure

Hmm, maybe was a bit too optimistic: I tried again with completely new activity names, but I get the same result: the first level of identation is fin...

11 years ago
Reply
Import activities with tree structure

OK, wasn't sure whether the use case had been tested already - it is quite possible that i have the same name several times, so i'll check on that fro...

11 years ago
Topic
Replies: 4
Views: 2630
Reply
[V5.2] Export to CSV: issues with 'description' field

OK, I understand - Good point ! 🙂 Thanks

11 years ago
Topic
Reply
Question about planning and Planned End Date

Hello, Most likely this is because you have 'real work' logged on 01/10. The 'planned end date' is actually the max of 'initially planned end date'...

11 years ago
Topic
Replies: 2
Views: 3140
Topic
11 years ago
Replies: 1
Views: 3485
Reply
Real work allocation design

Hello, Hoping this might help - we've made a customization to handle this issue in RWA screen. Whenever you scroll down, the column titles remain ...

11 years ago
Reply
Advice on closing projects

Good point on the reporting. I'll have to see if that can be an issue, since there isn't too much reporting done on closed projects anyway. In any ...

12 years ago
Topic
Replies: 2
Views: 3643
Reply
In which industry do you use projector / Dans quel secteur d'activité utilisez vous projector

I never did reply - I'm in a consulting services company, we use Projeqtor in multiple departments (IT, Systems Engineering,...) --- Je travaille da...

12 years ago
Reply
Sortable WBS not exported

That sounds like the best solution indeed 🙂 Thanks!

12 years ago
Topic
Replies: 2
Views: 3539
Reply
Migrate existing project to Projeqtor (with real work)

I'll give that a try ! Thanks 🙂

12 years ago
Topic
Reply
Cost for the meetings

I agree with Evgueni, this could make it better to see the whole cost of a project. Perhaps one solution would be to make it similar to tickets ? I...

12 years ago