Welcome to ProjeQtOr new Forum. We migrated old forum to the new website.
You will find all your posts here, with your usual account.
Just one point : you’ll have to reinitialize your password. Use “Lost password” feature.
Last seen: 30 Jun 2020 16H26
Hi, I'm using Google chrome. I have plugin but how do I see which one is affecting it?
There are several reports to do this There are only hours in the reports, I would like to see percentage. Just close the project.It will close all...
Yes, it is good option (the one I use when I have no specific constraint). Now I came across another problem. If I set all resources to 100% allocati...
It's the "Global planning project/resource per month" report. I'm using V8.0.2
Hi, I see that the bug has fixed however the sum numbers are still decimal numbers.
Aha, it's my browser that is zoomed out for some reason so I didn't see the table. Thanks!
Thanks!
Thanks! Now I see, but the orange center is very small and not very easy to see in my opinion. I have missed it the whole time.
Is it a bug then? Although it's not a big issue it doesn't look good when I want to present it to our manager.
OK, thanks!
- on project view, you'll see "need planning" in progress / steering section Could you please post a screenshot, I can't find the progress/steering...
aha, now I know. Do you suggest that I set 100% on all projects and the assignment rate for different activities?
OK, I think I understand now. When I add a resource, it checks if the resource is available now, if I don't set the end date the person would be avail...
If I don't set an end date then he will have 200% allocation if he has another ongoing project, won't the calculate go wrong in this case? I confirm t...
Is that a 1st April joke? :') We are not time travellers but we need to add projects that started earlier and continue the planning if you understa...
But it's an activity in January that I want to change the resource.
:(, that'll be a hell of work. I think I understand more how it works now. 🙂
I realized that I have misunderstood the project rate and the activity assignment rate for a resource. I changed some of them and now it looks much be...
Ah, I see... Actually, the activity is ok now, I don't know what I have done. But the same problem occurs for other activities as well.