Welcome to ProjeQtOr new Forum. We migrated old forum to the new website.
You will find all your posts here, with your usual account.
Just one point : you’ll have to reinitialize your password. Use “Lost password” feature.
Last seen: 24 Oct 2016 16H13
I think I've the answer, I can change it on the "Type of project" and change the default workflow, is it the correct way?
What's happen if the two activities have the same priority? ProjeQtOr choses one with "random logic" to plan?Default priority is WBS order. What's ...
Ok, but to re-eavaluate, I change the assigment work for each ressource or I change the work on the progress task section?
Sure, I will do it to avoid any problem.
Ok, it is more clear. If I want to reevaluate a task, what's happen if my plan work was 10d and the Real Work Allocation is 10 d, how can I reevalu...
Data was not lose during upgrade process? Just to be sure 😉
And it isn't depend to the number of assigned ressources... it is better. 👿
Thanks a lot Babynus, you are right. :woohoo: It is easier than with change the different rates!!! But I'm not sure why it is correct? it i...
so, if I have my configuration in my test case is: 33% Project 1 ---> "regular between dates" ---> cyclic tasks 33% Projet 2 ---> "regule...
I'm not agree with you but just to be more clear, ressources have another projects to do every day. 33% Project 1 ---> "regular between dates"...
I tested on ProjeQtOr and my answer is : project assigment at 100% activity assigment at 33% Let me know if you are not agree
Sorry, I wrote a mistake, You assign 77 days on the task with 35% on project assigment and 100% on activity task, could you confirm me?
no ! First a year is not 365 days (in a workly basis) but about 220 (must exclude week-ends, off days, holidays). Then if eauc is 35% on the task,...
Ok, so if I have 7 people with each person is working 35% per day on this cyclic task, the formule is: 365 * 0.35 /7 = 18.25 days (total time * ...
Yes, I will do it for next question.
Sorry, you are right. 😳 It is because the user was created with Guest Profile (auto) ,I assigned some tasks to this user and I changed the p...
Hi Babynus One question more, my team is working on "real projects" and "run projects" (activities from day to day), so if I want to plan some proj...