Thanks Babynus, Have a good day
Thanks for your quick reply
Thanks Babynus, right now, it is more clear for me. What's happen if the two activities have the same priority? ProjeQtOr choses one with "random ...
Sorry for my english, the question was: How to detect overload on the same ressource?
You are a "Master", thanks a lot. Just to be sure, I assigned the work with the "change button" (pen) directly on the activity details on the Assi...
Thanks a lot Babynus, sometimes, one image explains better than 1000 words B)
It doesn't work, I attach the Gantt and the detail of activity.
Sorry but I don't understand. Your answer was for which ratio? Could you explain me again with this number? Project Screen: 100% Activity Sc...
I clicked on this button before send you the screenshot to generate the plan. I click again and the result is the same. Any explication?
Ah ok, for example, I affect 100% on the project screen and if I affect on the task 40%, so the ressource will work 0.4 day every day of the week, is ...
It takes sense but when I update the new value on "charge" field (ex: 7 days) without fill "durée" (with ASAP planification), the Grantt project doesn...
I try to assign directly on the Activity screen, but no resource is available (on the list), do you know why?
Thanks a lot, the translation was not difficult :blush: but your explication is good :woohoo: I will try this on your software, Thanks
Thanks for reply quickly, I use Projetqtor IDE in french, what is the name of the field to use "ressource affected" and "ressource assigned"? M...
Thanks for reply. If I work with ASAP planification method, I just fill "durée" field and it is enough. So, in which case can I use "charge"? ...