[SOLVED] Duration in planning mode

Sorry : in fact you must assign those 31 days to your developer :

Il y a 10 ans
Répondre
[SOLVED] Duration in planning mode

You must set the project workload in field "work" instead of field "duration".

Il y a 10 ans
Répondre
Sharing resources between business units

I guess it is ticket #1815 : Will be definitively interesting, and potentially would solve our issue It is targetted for 5.4.0, can't wait for thi...

Il y a 10 ans
Répondre
Searching projects in selector

Sorry I should have searched first First ticket targeted for V5.4.0, great ! Thanks

Il y a 10 ans
Sujet
Replies: 2
Views: 4026
Répondre
Sharing resources between business units

Thanks Since we do this kind of operation very often, it will be a lot of confusing manual operations (and my colleagues will hate me for that 🙁 ...

Il y a 10 ans
Répondre
[SOLVED] How the planned dates?

In "planning" view, click on calculate button Check manual :

Il y a 10 ans
Répondre
[SOLVED] How the planned dates?

I want to ask about planned ?. How to display the date in the plan. According to the document, it is automatically added. But I entered full, start da...

Il y a 10 ans
Sujet
Replies: 4
Views: 4414
Répondre
Real in progress vs real in assignment

Not the first 3 ideas, apparently It is more like 2 days have been removed from "real work" but not taken into account for some reason Maybe a bug...

Il y a 10 ans
Sujet
Replies: 3
Views: 3824
Répondre
Overspent days in planned days

What you propose will not work. It will if you enter days correclty day by day and never enter work backward. OK that's true :-/ But instead of t...

Il y a 10 ans
Répondre
Overspent days in planned days

Would it be easier to have 1 field in work and plannedwork table that would indicate the progress in the activity ? (so for Activities only) Progress...

Il y a 10 ans
Répondre
Overspent days in planned days

Why have it on planning element as you have it on Activity ? (this is a 1on1 link between both) Sorry, rather in in PlannedWork or in Work table, so...

Il y a 10 ans
Répondre
Overspent days in planned days

I want to distinguish the planned days in normal validated days from the planned days that are overspentYou cannot. Only margin will give you the info...

Il y a 10 ans