Budget planning with new TJ / Planification budgétaire avec nouveau TJ

Hello, We had planned a project in 2021 with the TJ 2021. With the change to 2022, some TJs have changed. I understand that the assignment has not...

5 years ago
Reply
Budget planning with new TJ / Planification budgétaire avec nouveau TJ

Hello, For your information I am working on version v9.2.4. I noticed that the recalculation of the left and the revised are only done if the as...

5 years ago
Reply
Budget planning with new TJ / Planification budgétaire avec nouveau TJ

Hello, The cost of my resource changes today (see attachment 1) but when I go to its activity, the old cost is always used to calculate the rest an...

5 years ago
Reply
Resource planning with validated entry sheet

Hello, I don't understand why when you validate the data sheet, the remaining days are not rescheduled for the next week? I think that validating ...

5 years ago
Topic
Replies: 3
Views: 1627
Topic
Replies: 1
Views: 2058
Topic
5 years ago
Replies: 1
Views: 1953
Reply
[SOLVED] Absence entry problem

Here (attachment) is the data entered (before the absence was entered) in the "Earned Absence Entitlement" screen for the resource listed in my first ...

5 years ago
Topic
Replies: 3
Views: 2372
Reply
[SOLVED] Open a new tab

When the resource uses the button it gives him the page with the error message and when he closes all the tabs and tries to reconnect to ProjeQtOr, it...

5 years ago
Topic
Replies: 5
Views: 1982
Reply
[SOLVED] impossible to display global planning after upgrade version 9.2.1 to 9.3.0

How possible would it be to have the release of version 9.3.0? Dans quelle mesure il serait possible d'avoir la release de la version 9.3.0?

5 years ago
Reply
[SOLVED] Problem with saved planning

I'm using the 9.0.4 version.

5 years ago
Topic
Replies: 1
Views: 1396
Reply
[SOLVED] Validated work treatment operation

Thank you for your answer. In this case, how can we track the supplier orders directly in the project? It is recommended to use the expenses only ...

5 years ago
Topic
Replies: 3
Views: 1781
Topic
Replies: 3
Views: 1599
Topic
Replies: 1
Views: 1267
Reply
[SOLVED] Link between "Work plan per resource and per week" and "Timesheet validation

Hello ! Don't forget that on this report you have the actual work (informed about the imputations) and the planned work. I can't seem to reprodu...

5 years ago