[SOLVED] Workload forecast

I finally found it : Report -> Planning -> Work Plan. Maybe some additional features could improve these reports, but this was what i sear...

4 years ago
Topic
Replies: 2
Views: 1320
Reply
Imputation - ERROR unsupported operand types : string / string

The Activity is set with planning mode "Fix Duration", and a duration is set (btw a start date and an end date, with the caldulated duration). The i...

4 years ago
Reply
pool of resources assignment to a reccuring meeting failed

This issue has been delivered in 10.0.2, thank you. I just test the newly 10.0.2 release. It remains an error when doing an assignment of a pool o...

4 years ago
Topic
Replies: 1
Views: 1455
Topic
Replies: 1
Views: 1473
Reply
manual planning & planning calculation

Thank you for you reply. Unfortunately the only way to modify duration -- and end date -- in my case was to drag the bar on the gantt chart. And thi...

4 years ago
Reply
manual planning & planning calculation

Thank you for your reply and help. Does this mean an assignment is mandatory to a manually planned task? I just would like to manually set start d...

4 years ago
Topic
Replies: 5
Views: 1622
Reply
Planned date & duration do not update

Thank you for all your replies. Once activites are listed and sequenced, planning an activity is partially based on calculation (activity resource...

5 years ago
Reply
Planned date & duration do not update

Well, attached is another example. I set the duration for a given task to 3 days, and set some workload (2h each). When click on calculator, it adjus...

5 years ago
Topic
Replies: 7
Views: 4068
Topic
Replies: 1
Views: 1214